Crews Use 1,000 Lbs. of Explosives for Demo of Navajo Generating Station Boilers

A contractor used more than 1,000 lbs. of explosives on March 3 to demolish the Navajo Generating Station's three 245-ft.-tall boilers. The coal-fired power plant near the Arizona-Utah border shut down in 2019 and three 775-ft. concrete stacks were imploded in December. The boiler demolition was part of Salt River Project's continuing decommissioning of the nearly 50-year-old coal-fired power plant near the Arizona-Utah border....