Crews Use 1,000 Lbs. of Explosives for Demo of Navajo Generating Station Boilers

A contractor used more than 1,000 lbs. of explosives on March 3 to demolish the Navajo Generating Station's three 245-ft.-tall boilers. The coal-fired power plant near the Arizona-Utah border shut down in 2019 and three 775-ft. concrete stacks were imploded in December. The boiler demolition was part of Salt River Project's continuing decommissioning of the nearly 50-year-old coal-fired power plant near the Arizona-Utah border....

from RSSMix.com Mix ID 8246474 https://ift.tt/3veJCzm
via Inchiriere buldozere - Tuscher & Milas Company

Comentarii

Postări populare de pe acest blog

Construction News – Museum of Idaho to Double in Size After $4M Expansion Project

New York's MTA To Repair Train Tunnel Hit by Hurricane Sandy

New Jersey Road Closures Begin for Long Lincoln Tunnel Approach Project