UMA Scales up Production on Unusually Large Soil Nail Wall

UMA Geotechnical Construction constructed all of the eight required permanent soil nail walls along a roughly 2-mi. stretch of the Greensboro Western Loop (Interstate 73) project but they were all dwarfed by the Wall 4. To be exact, the total project required 76,000 sq. ft. of wall, 42,000 of which was Wall 4....