Crews Race Time in R.R. Bridge Rebuild
This fall, Fay, an i+iconUSA Company, managed the design-build replacement of the Flat Rock River Bridge in Columbus, Ind., completing the project in only 50 hours, well in advance of a 96-hour outage deadline. The project was done for Louisville & Indiana Rail (LIRC), which is part of Anacostia Rail Holdings....